Wisconsin I-94 expansion project faces potential two-year delay

The Brief

  • A major I-94 expansion project in Milwaukee County could face a potential two-year delay.
  • A letter written by the Wisconsin DOT secretary said utility relocations along the corridor led to a 1.3% project cost increase.
  • The Wisconsin DOT is trying to reduce delays by shifting future budget funds.

MILWAUKEE It could be a big headache for drivers who take I-94 frequently. The massive project to expand a stretch of the interstate in Milwaukee County could take even longer than expected.

The Wisconsin Department of Transportation says this is primarily due to budgetary concerns.

I-94 expansion project

What they’re saying:

“The current estimate for the seven ongoing major projects, excluding SE Mega projects, is $6,437.3 million. This is $18.0 million, or 0.3%, higher when compared to the same seven major projects from the February 2026 estimate,” the Wisconsin DOT secretary said in a letter addressed to the Transportation Projects Commission.

The report went on to say the project now “shows a 1.3% cost increase when compared to the February 2026 report.