Asbestos discovery delays construction of new athletic facility

Construction of Northeastern’s new Multipurpose Athletics and Recreation Facility has been delayed about nine months, now set to be completed in spring or summer of 2029 rather than the fall of 2028, according to an Aug. 25 email shared with The Huntington News.

Asbestos-containing material likely left from the original construction of the arena, which was constructed in 1910, was discovered upon excavation, prompting a suspension of work and consultation with the Massachusetts Department of Environmental Protection, Senior Vice President for Finance and Administration Brett Sweet wrote in the email.

The delay also means that the men’s and women’s hockey teams will likely spend a third season without a home rink. The construction of the new facility will cost upward of $350 million, according to Northeastern’s 2024 institutional master plan…