$165 Million I-77 Overhaul in Fort Mill Delayed Into 2028

One of York County’s biggest highway projects just got delayed…by a lot.

The $165 million rebuild of I-77 Exit 85 at S.C. 160 in Fort Mill is now expected to finish May 30, 2028 – a project that was originally scheduled to open in November 2027.

SCDOT officials say utility relocation caused the roughly six-month delay. The added time is not expected to increase the project’s cost.

South Carolina’s First Interchange of Its Kind

The massive Exit 85 project serves the fast-growing Baxter Village and Kingsley areas and is designed to completely reshape traffic around S.C. 160…