Jones Bridge Road Widening Delayed Until Spring 2027

Drivers waiting for construction to finish on Jones Bridge Road between Douglas and Sargent roads will have to wait until spring 2027, Johns Creek officials said Friday.

The project had been expected to finish this fall. In an Oct. 16 update, the city attributed the revised schedule to utility relocation delays that have held up the remaining roadwork.

The widening project will create a four-lane divided section with medians and turn lanes, along with improvements at the Douglas Road intersection.

Utility work must finish first

Comcast completed its relocation work in early October, and Charter is now finishing its portion, according to the city. AT&T will follow as the last utility relocation needed before existing poles can be removed…