Dominion’s $874M Power Line Plan Faces Richmond Hearing as Counties Push Back

A high-voltage transmission line proposed to run between Fauquier and Loudoun counties landed before Virginia regulators Monday, as the State Corporation Commission opened an evidentiary hearing on Dominion Energy’s roughly $873.6 million Morrisville-to-Wishing Star project. The hearing, which began at 10 a.m. in Richmond, will determine whether Dominion gets the green light to build a new 500-kV line stretching across three Northern Virginia counties that have already pushed back on the plan.

Dominion filed its application with the commission on February 27, 2026, seeking approval for what it calls Line #5008 — an overhead 500-kV line connecting the Morrisville substation in Fauquier County to the Wishing Star substation near Arcola in Loudoun County, according to Construction Review. Reported route lengths vary: Patch has put the line at 36.5 miles, while Fauquier.com describes it as 36 miles. A separate figure — 34.5 miles — refers specifically to the portion running along or near existing right-of-way, as reported by Loudoun Times, and should not be confused with the project’s total length.

What’s Actually in the Application

Beyond the headline transmission line, Dominion’s filing covers a second, smaller line — an approximately 8.1-mile 230-kV connection between the Morrisville and Anderson Branch substations, which would be built alongside existing infrastructure. The utility also proposes rebuilding multiple existing 500-kV and 230-kV lines and expanding the Morrisville substation itself, per Construction Review’s reporting on the filing.

In parts of Loudoun County, Dominion wants to swap existing lattice transmission towers for monopole structures, with Line #5008 supported by galvanized steel monopoles. Patch reports that the 4.8-mile Loudoun County segment follows a transmission corridor that was already slated for rebuilding before this project emerged. Loudoun Times has also reported that Dominion dropped three alternative routes through Loudoun County after hearing from local officials and residents.

Counties Question the Need

Fauquier County, the Piedmont Environmental Council and the American Battlefield Trust have all raised questions about whether the project is necessary, how its route was chosen, and what impacts it could have, according to Construction Review’s account of the filing. Dominion, for its part, points to PJM Interconnection reliability violations identified during its 2022 and 2024 regional transmission expansion plan cycles as justification, saying the project addresses future electricity demand and the reliability of the regional transmission system…

Story continues