Contractor wants out of Boynton Beach project, says city owes over $300K

BOYNTON BEACH, Fla. (CBS12) — A West Palm Beach construction company is suing the City of Boynton Beach, alleging faulty plans and an unpaid change order stalled a $798,225 boat ramp project.

Mangonia Construction Group filed the lawsuit Oct. 30 over the Pioneer Canal Park Boat Ramp and Driveway Reconfiguration Project. The company is asking a Palm Beach County judge to let it terminate its contract and order the city to pay for work and expenses it says remain unpaid.

The lawsuit claims Mangonia discovered problems with the city’s project design in April and told the city the work could not move forward as planned. According to the complaint, the city directed the company to do additional work under a revised design, but that design also failed to address the site conditions…