CINCINNATI, Ohio — The next wave of Brent Spence Bridge corridor closures now has dates on it: the Gest Street ramp to Seventh Street closes permanently on Tuesday, December 1, 2026 for partial demolition of a garage, and a set of downtown Cincinnati ramps and bridges follows in January 2027, project spokespeople said at a November 9, 2026 media briefing at Longworth Hall, The Cincinnati Enquirer reported.
The $4.39 billion Brent Spence Bridge Corridor Project will be under construction through 2033, The Cincinnati Enquirer reported. It will build a new, still-unnamed double-decker companion bridge directly west of the Brent Spence Bridge, carrying 10 lanes of through traffic, while the existing 63-year-old bridge is renovated to carry six lanes, primarily for local traffic. The Brent Spence carries about $1 billion worth of freight and roughly 160,000 vehicles a day, The Cincinnati Enquirer reported.
The January 2027 closures are the long ones, The Cincinnati Enquirer reported: the Ninth Street ramp to southbound Interstate 75 closes for about three years; the Seventh Street ramp to southbound I-75 for about two years and two months; the Eighth Street ramp to Seventh Street over I-75 for about 18 months; and the Sixth Street bridge over I-75, from Central Avenue, for about 18 months. An eastbound U.S. 50 ramp to southbound I-75 also closes in January 2027 and is expected to reopen in mid-January, The Cincinnati Enquirer reported…