The expansion of the SmartWay Intelligent Transportation System (ITS) on I-40 near I-840 in Dickson County to near U.S. 70S (Exit 196) in Davidson County will potentially impact travel from Feb. 8-14.
• Daily 7:30 a.m. – 6 p.m. There will be temporary daytime shoulder closures in both directions for conduit installation at various locations throughout the project limits. (MM 174-196)
• Nightly, 8:00 p.m. – 5 a.m. There will be temporary nighttime shoulder closures in both directions for conduit installation at various locations throughout the project limits. (MM 174-196)
HICKMAN COUNTY I-40
The repair of the bridges on I-40 over Sugar Creek and Resurfacing on I-40
LOOK AHEAD 2/16, 7 p.m. continuously until 5 a.m., 2/19, There will be continuous weekend lane closures on I-40 WB for bridge repair work. One lane will remain open at all times. MM 150
WILLIAMSON COUNTY I-840
The installation of longitudinal cable barrier on various interstate routes
• Daily, 9 a.m. – 3 p.m., There will be daytime Shoulder closures to install cable barrier post and cable for the new cable barrier system at MM 6-7 and MM 28-29