More than three years into a $242.7 million overhaul of U.S. 19, the construction company rebuilding the highway is accusing Pinellas County of contributing to delays that county officials say have put the project more than two years behind schedule.
Representatives of Johnson Brothers Corporation appeared before the Pinellas County Commission Tuesday to oppose a plan to hire another contractor to complete some of their work. They contend that design problems and lengthy waits for revised construction plans have hampered the project.
Commissioners voted 4-3 to approve a $10 million increase to an existing utility repair contract with QRC Inc., approximately $4.5 million of which is intended for work associated with the highway reconstruction…