COLORADO SPRINGS, Colo. (KRDO) — The two-year, $15 million Dublin Improvements Project continues to move eastward, with the latest phase starting this month.
This phase affects Dublin Boulevard several blocks east of Marksheffel Road, including the intersections of Issaquah Drive and Van Winkle Drive.
Along the affected blocks of Dublin, crews removed the center median and have shifted all traffic to the north side of Dublin.
Removing the median created space to make a temporary left-turn lane into businesses on the south side of Dublin.
Coming soon are traffic signals at the Dublin/Issaquah intersection. That installation is in progress.
Eventually, that segment of Dublin will expand from two to four lanes and include new, wider sidewalks…