DAHLONEGA, Ga. — Drivers traveling between Dahlonega and Cleveland on Highway 52 East will encounter a new traffic pattern beginning Monday, Nov. 23, as traffic shifts onto the newly constructed bridge over the Chestatee River.
The Georgia Department of Transportation (GDOT) is preparing to open the bridge to traffic in both directions while crews continue work on the remainder of the project.
The approximately $10 million bridge replacement project is running about a month behind schedule. Originally slated for completion Nov. 30, the project now has a Dec. 30 completion date, according to GDOT records…