Demolition work has finally started on the Kimberly-Clark paper goods warehouse in Ontario, months after it was destroyed in a massive fire that was allegedly started by an arson suspect in April.

Now, for at least the next two weeks, demolition crews are expected to work for up to 12 hours a day as they work to remove the exterior concrete walls of the building before they start clearing out the debris left by the April 7 inferno.

Ontario city officials had previously told CBS LA that the demolition process was supposed to begin in May, but work was pushed back until Monday…