Road Warrior: Poles still in the way of starting Monclova roundabout

After yet another postponement, construction of a roundabout at Monclova and Albon roads in Monclova Township is now scheduled to start June 15.

With the Lucas County Engineer’s Office blaming late relocation of Toledo Edison poles for delaying the project well past its original late-April start, I paid the site a visit Friday.

Utility crews were working that afternoon on poles at Monclova’s nearby intersection with Waterville-Monclova Road. New poles were all standing at Albon, but the old poles remained in the roundabout’s path with telecommunications cables still needing to be moved…