I-59 northbound ramps at Chalkville Mountain Road reopen in Trussville

Traffic began flowing on the reopened exit and entrance ramps June 26, according to ALDOT. The ramps had been closed since May 18 as part of the ongoing I-59 widening project.

Contractor Wiregrass Construction Co. was incentivized to reopen the ramps within 40 days of the closure and did so ahead of schedule, ALDOT said.

“ALDOT appreciates the contractor’s diligence to reopen the ramps quickly to minimize the impact of the ongoing I-59 enhancements,” the department said in a release…