Construction on Liberty Street between Douglas and Denton streets was supposed to wrap up this month. But now, ACHD is terminating its contract with the company behind the project, pushing completion into next summer.
WATCH: Why the Liberty Street project is delayed
ACHD drops Liberty Street contractor, delaying Boise Bench road project
Crews plan to repave Liberty Street and reopen it to two-way traffic before winter, but that pavement is only temporary.
“The most important part of the road is the material underneath it, the gravels, and they haven’t replaced the gravels yet,” said Matthew Gibbs, a project inspector with ACHD…