  • Repairs to Grafton’s Bridge Street dam on the Milwaukee River will resume in spring.
  • A hydraulic cylinder failed in May, and repair work was approved in August.
  • The Wisconsin DNR said amphibians are burrowing into the area for the winter.

GRAFTON, Wis. – Water has been rushing through one side of Grafton’s Bridge Street dam on the Milwaukee River since May, but the work to fix the issue is on hold – due to burrowing amphibians.

Grafton dam failure

The backstory:

The dam’s hydraulic cylinder failed in May. The Grafton Village Board passed a motion in August to repair the dam and solicit bids to complete the work.