RAPID CITY, S.D. (KOTA) – Black Hills Energy is asking South Dakota regulators to delay a new monthly customer charge tied to its Lange II power plant until February 2027, after the facility is expected to begin operating.
The natural gas power plant is under construction in Rapid City and was originally scheduled to enter service Dec. 1. But supply chain delays have pushed the expected completion date to January 2027.
Black Hills Energy is asking the South Dakota Public Utilities Commission to postpone the Phase-in Plan Rate, which will help the company recover costs associated with the project…