University of Michigan Approves Nuclear Lab Data Center; Township Vows Suit

A clears the path for a $1.25 billion project where Los Alamos National Laboratory would occupy roughly 90% of capacity. Ypsilanti Township says it will sue.

The facility would occupy a 144-acreTextile Road site, described in university materials as a 124-acre development parcel plus a separate 20-acre parcel set aside for electrical infrastructure. Construction is expected to begin in late 2027, with the facility expanding across two phases to approximately 290,000 square feet.

The regents authorized construction costs of up to $785 million for both phases. The total project investment has been reported at approximately $1.25 billion, with the first phase estimated at roughly $450 million.

Facility Use Split Is Central to the Dispute

According to reporting, Los Alamos National Laboratory would occupy roughly 90% of the facility, while U-M would use approximately 50,000 square feet, or about 10%.…