Sellersburg has approved new zoning regulations for data centers, solar farms, and energy storage facilities, closing a gap in the town’s development rules that previously let developers argue these projects could be built in industrial zones without dedicated standards. The town now has two new zoning categories on the books, but as of day one, no land within Sellersburg is actually zoned for either one.
Two New Districts, No Land Zoned Yet
The regulations, reported by WLKY, establish a Solar Energy District and a Data Center District as separate zoning classifications. According to the town’s own plain-language guide published by sellersburg.org, no land within the town currently falls into either district, meaning any developer would have to seek rezoning for a specific parcel before building anything. That rezoning path requires applicants to present their case to the zoning planning commission, which then makes a recommendation to the town council, per WLKY. Indiana state statute requires public hearings for zoning changes, and under the new framework every project needs two separate approvals, each with its own public hearing.
Sellersburg Town Manager Charlie Smith said any such facility would have to go through the town’s rezoning process and a public process before it could move forward, according to WLKY. Smith said the proposed changes include letters being sent to affected parties, and the town’s guide specifies that neighbors within half a mile of a proposed project would get notice by mail. The Sellersburg Town Council holds final authority over these proposed uses, with decisions following recommendations from the planning commission.
Why The Old Rules Fell Short
The gap stemmed from how the town’s prior unified development ordinance was written. The existing ordinance permitted commercial solar energy facilities by right in the general agriculture district but did not address data centers or battery storage facilities at all, according to the News and Tribune. That silence on data centers and battery storage is what allowed developers to argue, under the previous ordinance, that such facilities could be built in industrial zones. The Sellersburg Plan Commission responded by voting to recommend creating the solar and data center districts with tight restrictions on potential developments, the paper reported.
The updated draft followed four public input sessions held in August that drew 16 people offering feedback and suggestions about development in town, the News and Tribune reported in earlier coverage. Within Sellersburg town limits, two properties have the capacity to accommodate these kinds of developments, according to WLKY.
Setbacks, Acreage, and Noise Limits
The standards themselves are detailed. Solar farms must cover at least 40 acres, per the town’s guide, while data centers must sit on sites of at least 50 acres, with no more than half of that acreage paved or built upon. Data centers must also stay at least 1,000 feet from homes, and the guide is explicit that there are no exceptions to that distance. Noise at the property line is capped at 50 decibels during the day and 45 decibels at night, and water and sewer utilities must confirm in writing that they can serve a proposed data center without reducing service to existing customers…