Infrastructure, roadway projects: Here’s what’s planned in Citrus Heights

By Sara Beth Williams– — Several major road projects are currently being planned throughout Citrus Heights, with a major infrastructure project recently approved by the City Council and others still in the proposal stage.

2026-27 Drainage and Accessibility repairs:

  • The 2026 and 2027 Accessibility and Drainage Project, approved in July, includes construction of 240 accessible curb ramps, repairs to 28,900 square feet of sidewalk and 3,500 linear feet of curb and gutter, and reconstruction or relocation of 45 storm drain structures. The project also includes replacing 3,365 linear feet of deteriorated storm drainpipe, crack sealing 49 roadways and completing 354,500 square feet of asphalt dig-out repairs. This project takes places usually throughout the fall, winter, and into spring and precedes road resurfacing projects.
  • The same project also includes two potential additives, with added cost, of curb ramp installations outside the main planned resurfacing areas. Three ramps are proposed at Dunmore Avenue and Shadow Oak Drive, near the entrance to Brooktree Park, and two ramps are proposed at Mariposa Avenue and Grace Ellen Court, along a designated Safe Route to School. The project is expected to begin in the fall 2026.

Greenback Lane:

  • As part of the same above project, additional improvements are planned along Greenback Lane between Mariposa Avenue and Birdcage Street, where the existing fence will be removed and the existing median reconstructed. As well, the city plans to install a new pedestrian crosswalk and signal phase on the west leg of the intersection at Greenback Lane and Birdcage Street.
  • The city also recently announced the receipt of a $3.5 million grant that they say will go toward funding infrastructure improvements along Greenback Lane from Dewey Drive to Birdcage Street, and along Auburn Boulevard from Manzanita Avenue. The exact scope of what the planned projects will tackle has not yet been announced.

Carriage Drive:

  • At Auburn Boulevard and Carriage Drive, the Drainage and Accessibility project will incorporate improvements identified in the city’s adopted Carriage Drive-Lauppe Lane Safe Schools Corridor Plan, including, two ADA compliant extensions, widening the sidewalk on the north side of Auburn Boulevard between Carriage Drive and Sylvan Middle School, installing a raised median on the east leg of Auburn Boulevard and adding a pedestrian crosswalk and signal phase on the west leg of the intersection.
  • In the city’s recent Local Roads Safety Plan, the city has also identified various infrastructure and construction projects and is currently seeking grant funding for two. The first includes safety improvements along Carriage Drive and Lauppe Lane. Improvements proposed include construction of curb extensions, improvements to raised crosswalks, and installation of speed humps and radar speed feedback signs.

City-wide improvement proposals:

The second project being submitted for grant funding includes city-wide sign and traffic safety upgrades, which includes replacing traffic regulatory and warning signs in the eastern half of the city, adding missing all-way plaques and radar speed feedback signs in select roadways…

Story continues