Road Development Updates November 2024

Corkscrew Road Widening – Ben Hill Griffin to East side of Bella Terra. The road widening and related utilities movement, Lee Department of Transport’s (LDOT’s) contractor, nears completion with Phase 1 (from Ben Hill Griffin Pkwy. to Bella Terra Blvd.). Starting in early 2025, the Village of Estero will install shared-use paths, lighting, and landscaping. Once a contractor has been selected, the Village of Estero’s efforts are projected to take 6 – 9 months. However, long lead time items (e.g., streetlight poles) may extend the timeline.