Incline Beach House nearing next steps

INCLINE VILLAGE, Nev. – The Incline Village General Improvement District met last Thursday to discuss updates to the Incline Beach House Project, a new tennis center play pass program, and an expanded fire agreement.

Board members started with an update on the Incline Beach House Project, which is nearing final decisions. “I’m excited to see the community feedback and see where they stand as we start to make final decisions,” said Michaela Tonking.

As of June 24, the design-build team at CORE Construction has submitted design development drawings and will proceed with construction drawings, scheduled for submission by the end of August. The project has been in progress for nearly a decade, and nearing this stage of the process marks a step closer to making the developments tangible…