Maryland regulators on Friday set a procedural schedule for reviewing the Piedmont Reliability Project, a proposed 67-mile transmission line through Baltimore, Carroll and Frederick counties.
The Maryland Public Service Commission approved a timeline that extends beyond what developer PSEG requested.
The New Jersey-based utility asked the Commission to issue a decision by March 31, 2026, so it could finish construction and have the line in service by June 1, 2027…