–photo courtesy of MDTA-
Maryland Department of Transportation Authority gave an update on the Key Bridge demolition and they reported landside removal is complete on both the north and south sides.
That includes 70,000+ linear feet of concrete sawcuts completed, 24,000+ cubic yards of bridge concrete removed and recycled, 10,000+ cubic yards of piers demolished and 175 girders removed and recycled…