Work Underway on 425K-SF Plano Data Center

Data center development continues at a site in southeast Plano. Aligned Data Centers is advancing on the construction of a 425,000-square-foot, two-story building at 601 N. Star Road.

It’s being developed in phases for Lambda Inc., a cloud-computing company backed by Nvidia. The $700 million project will eventually have 72 megawatts of computing power and is expected to be fully completed next year

The first 9 megawatts will be ready for Lambda to begin installing servers in June, with additional capacity coming online in 9-megawatt increments as construction progresses. Work on the project began in 2024. In addition to Aligned, the development team includes Turner Construction Co., Olsson, WSP and Corgan…