Battle Ground extends closure of Northeast 92nd Avenue for Cherry Grove utilities work

The City of Battle Ground has extended the closure of Northeast 92nd Avenue bordering the west edge of city limits between Northeast 239th Street and state Route 502/West Main Street as utility work tied to the Village at Cherry Grove subdivision continues past its originally expected October 2025 completion.

City officials re-issued a right-of-way permit allowing a contractor to resume work on utilities and road repairs along Northeast 92nd Avenue between Northeast 239th Street and state Route 502. The closure, which began in August, will extend to July 17.

The road will remain closed to through traffic during that time, though residents within the closure area and visitors to Cherry Grove Church will still have limited access depending on construction activity…