Columbus city staff answer questions about Buena Vista Road interchange, trash

Columbus Consolidated Government staff discussed the completion timeline and trash associated with the Buena Vista Road diverging diamond interchange project, led by the Georgia Department of Transportation, during Tuesday’s Columbus Council work session.

The Buena Vista Road project is about 77% complete, according to a presentation by Vance Beck, Columbus director of engineering, during the meeting. This project was reported as being about 75% completed during an infrastructure update presented to the council last October.

It has a budget of about $52.7 million as of Tuesday, according to information provided to the Ledger-Enquirer by deputy city manager Pam Hodge, with about $46 million already committed. According to the CCG data, the Buena Vista Road project is now estimated to be completed this winter…