Walnut Street Bridge restoration more than 30% over budget, Chattanooga councilwoman says

CHATTANOOGA, Tenn. — Concerns are growing at Chattanooga city council as the restoration of the Walnut Street Bridge continues.

Councilwoman Jenny Hill says the project is more than 30-percent over budget.

Jerramy Wood with Chattanooga Public Works says the project is complex, and crew continue to find problem areas.

“I think a lot of stuff with the Walnut Street Bridge was ‘sight unseen.’ So, whenever the contractors got into it, it was worse than what we anticipated. There was a lot of structural damage that was in there as far as the fluctuation with the integrity of the steel beams,” Woods says.

Construction began March 17, 2025, with an 18-month timeline that points to a late September 2026 reopening…