U.S. Higheay 93 widening project near Wikieup approaching halfway point

The project is adding more four-lane highway between Phoenix and Nevada

Contributed Article/Courtesy ADOT

PHOENIX – The Arizona Department of Transportation is nearing the halfway point on a project that is constructing 4 miles of a divided four-lane highway on U.S. Highway 93 between the Phoenix area and Las Vegas.

The $80.6 million project is now 45% complete as work continues to widen the two-lane segment of U.S. Highway 93 between Wikieup and Interstate 40 (mileposts 106-110). Since work began in January, crews have completed earthwork for the highway’s new southbound lanes…

Story continues