30th Street Bridge opening delayed until 2026

INDIANAPOLIS — The historic 30th Street Bridge was originally estimated to reopen by now. Instead, people have to wait at least two more years to cross the White River again.

https://img.particlenews.com/image.php?url=3iARzu_0woh2Lua00 WRTV

The Indianapolis Department of Public Works posted on social media Friday that work on the bridge is now expected to finish in late 2026. The agency said it could partially reopen to traffic by spring 2026.

https://img.particlenews.com/image.php?url=3NjAYA_0woh2Lua00 WRTV

When it first closed in May 2022, DPW told WRTV it hoped to open the 30th Street Bridge by fall 2024. However, the bridge is still largely incomplete as of now.

https://img.particlenews.com/image.php?url=2xMs2y_0woh2Lua00 WRTV

In a statement to WRTV, DPW said the main issue behind the delay was bad materials.

We had previously found some of the materials that were delivered to be unacceptable for usage. While this delayed the timeline of the project, Indy DPW remains fervent in providing a sufficient project to the residents of Indianapolis. We held our contractors accountable and are happy to share that work has started back up.

-Auboni Hart, Indianapolis Department of Public Works