FM 1463 Expansion in Katy and Fulshear: End Finally in Sight But Still Months Away

KATY and FULSHEAR, Texas (Covering Katy News)— The Texas Department of Transportation expects to complete the $108 million 6.7-mile expansion of FM 1463 by late 2026, more than four years after construction began.

The project involves expanding FM 1463 from two lanes to six lanes north of Spring Green Road, and from two lanes to four lanes with raised medians south of Spring Green Road. Work began in February 2022.

New Concrete Lanes Expected by January

Kris Hadley, TxDOT public information officer, said by January new northbound concrete main lanes will be placed from FM 1093 to Cinco Ranch Boulevard, continuing north to Cinco Trace and ending at Westridge Creek Lane.

By mid-2026, Hadley said, TxDOT estimates completing permanent intersection signals, sidewalks and crosswalks, and placing grass and vegetation along the new right-of-way.

Community Concerns Over Project Timeline

As TxDOT begins its fourth year on the project, some have complained about the time needed to finish the work. Hadley said TxDOT has received complaints about remaining utility issues, which it is addressing with Zachary Construction, the contractor. Right-of-way issues were resolved in 2022, she said…