Metro is nearing the finish line for two new extensions of the D Line. Though the anticipated opening dates have been delayed somewhat, both extensions – to Century City and to Westwood – are expected to open in 2027.
At the end of next year, D Line riders will be able to travel from Westwood to downtown L.A. in about 25 minutes. In less than a year, riders will go from Century City to downtown in 20 minutes.
In 2014, Metro began construction on nine new miles of heavy rail subway extending from Koreatown to Westwood. The project includes three extensions:
- D Line Section 1 is 4 miles from Koreatown to Beverly Hills: opened in May
- D Line Section 2 is 2.5 miles from Beverly Hills to Century City: 95+% complete
- D Line Section 3 is 2.5 miles from Century City to Westwood: ~90% complete
Last week, the Metro Board Finance Committee approved a cost increase [staff report, presentation] for D Line Section 2. The committee approved a $300 million budget increase, taking Section 2 costs from $2.57 to $2.87 billion.
Metro Chief Program Management Officer Tim Lindholm reassured the committee that this is the “final budget increase” that “gets us to the end – and opening” of this Section 2 project…