The expansion of Bartlett Dam northeast of Phoenix isn’t projected to be complete until 2045, a decade later than initially expected.
Why it matters: The project would capture more water on the Verde River, and with major cuts coming to the Valley’s allotment from the Colorado River, we need all the water we can get.
Catch up quick: The dam was built in the late 1930s to form Bartlett Lake and is operated by the Salt River Project (SRP).
- Earlier this decade, SRP, a host of Valley cities and the U.S. Bureau of Reclamation began exploring an expansion to capture water that would otherwise be lost to runoff.
- SRP wants to raise the dam’s height by 100 feet, which it says would hold enough additional water to supply a million households for one year.
State of play: The project was initially expected to be complete by 2035, but SRP informed stakeholders in August that it had been pushed back.
- Phoenix water resources management advisor Max Wilson tells Axios that the initial plan was to do all the permitting for the dam project simultaneously, but Reclamation is now asking that it be done sequentially.
- Without the expansion, SRP has had to send excess water down the river and into the Salt River during heavy rains, including roughly 200,000 acre-feet earlier this month.
- Meanwhile, Arizona is set to lose 760,000 acre-feet of Colorado River water annually — more than 247 billion gallons — under a federally imposed plan starting next year.
What they’re saying: “The federal government has made choices that significantly reduce the availability of Colorado River water,” Wilson says, adding that the feds should “speed up the projects that are necessary for us to be able to live in that world that they’ve created for us.”…