Wisconsin’s first Buc-ee’s now has a detailed construction clock. Our previous Wisconsin Buc-ee’s update covered the start of site work and the city’s early-2028 expectation; the project’s construction manager has since published a more specific 500-day schedule.
Cleveland Construction says work began in August 2026 and is targeting substantial completion in December 2027. That is a construction milestone—not a confirmed store-opening date—but it gives Wisconsin drivers a clearer view of how the build is expected to unfold.
What crews are working on now
The builder’s current project page says crews are handling mass excavation and underground utilities. The tank field and building foundations are expected to follow, placing the project firmly in active construction rather than planning or permitting…