$28 million public works facility approved in South St. Paul
By Jake Spitzack | Staff Writer |
In December, the City of South St. Paul will accept construction bids for one of its biggest ticket items in years: a new Public Works facility. Total project cost is expected to be approximately $28 million, with construction costs estimated at just under $24 million.
The existing public works facility at 400 Richmond St. was built 56 years ago and is woefully undersized and outdated. A 2023 municipal facility needs assessment identified more than $6.5 million was needed for system and safety upgrades – $2.4 million more than the property’s appraised value. At 74,000 square feet, the new facility will be more than twice the size, and it will be built on an approximately 7-acre site on Verderosa Avenue, just southwest of the DNR boat launch and Wakota trailhead. Construction is slated to begin by next summer, with the facility becoming operational by late 2028.
The final design for the new building was created by HCM architects and approved by the city council in October following a public hearing. City documents call the project a “generational investment” that will serve the city at least another 50 years. The City’s public works department has more than 20 employees and is responsible for a wide range of essential city infrastructure and services. It maintains streets and utility systems such as water and sewer, upkeeps city landscaping and park facilities, and stores and maintains the city’s heavy equipment and fleet of service vehicles, including South Metro fire trucks, police cruisers and snowplows. The new facility will feature secure employee parking and access, dedicated work areas for each division of the department, conference and breakroom spaces that can also support emergency operations during critical events, a city vehicle fueling station, water filling station for use by the city and commercial users, ample indoor storage and a vehicle wash bay. A separate storage building will also be made for the police department.
Verderosa Avenue is currently being extended to accommodate the new facility, as well as redevelopment work that is ramping up at the nearby Hardman Triangle site. The city’s community garden and longtime yard waste drop-off site were both closed to make way for the road extension. However, the garden is expected to reopen elsewhere in the city next year.
Funding
The city council recently approved a $21 million bond sale to finance a portion of the work and cash reserves and proceeds from the sale of the existing Public Works facility are expected to cover the rest. The current facility is being sold to AVR LLC, which will construct a concrete batch plant onsite and retain the existing building for storage. The bonds will have a 30-year term. Bond financing is a common approach for the construction of major public facilities. The city last issued bonds for the construction of Kaposia Landing and improvements at the former Wakota Arena, now called Doug Woog Arena.
The land was transferred to the city by Metropolitan Council Environmental Services at no cost because of challenging soil conditions that make private redevelopment unlikely. Ultimately, the city saved an estimated $1.05 million in land acquisition costs, and this spring, the Minnesota Legislature approved $2.25 million in state funding for soil remediation and environmental cleanup.
The city was also awarded $3 million from the U.S. Department of Housing and Urban Development for the extension of Verderosa Avenue and related public utilities. Minneapolis-based Kraus-Anderson has been retained as construction manager since 2024 to help oversee financing and construction. For project updates, visit southstpaulmn.gov.