How the new Commercial Street Bridge will be slid into place

Now that the old Commercial Street Bridge is down, the new bridge will be front and center as it’s slid into place. It’s a monumental task, but the company tasked with it, Mammoet, said it’s nothing new to them.

About 22 million pounds of steel, concrete and metal need to move only a short distance, but don’t expect it to be a quick process. The max speed of the skid shoes is 6 meters an hour. That’s roughly 20 feet.

“You’ll need to get your timelapse camera out in order to see something happen at a reasonable speed,” Mammoet public relations manager David Shaw said…

Story continues