A stalled North Portland apartment building that once budgeted its units at $361,000 apiece will now cost nearly $1 million each to finish, after the Oregon Housing Stability Council voted on Oct. 2 to pour an additional $30 million into the project. The vote brought the total cost of the 57-unit Monarca development to $56.2 million — an average of $985,513 per apartment — even as two council members refused to support it.
The council approved the extra funding despite abstentions from Ed McNamara, a retired Portland affordable housing developer, and Javier Mena, the affordable housing manager for the city of Beaverton, according to the Oregon Journalism Project. Three other council members voiced concerns about the project’s price tag but voted to fund it, while three voted to fund it without objection; council member Mary Ferrell was absent from the vote. Monarca, located at 1220 N Jessup St. in North Portland, sits in an eight-story building that will rent its apartments to households earning 60% or less of the area median income.
A Project That Stalled at the Halfway Mark
Monarca was formerly known as Minnesota Place, and construction on the project began four years before the council’s latest vote. It was initially budgeted at $26 million, or $361,000 per unit, but work stopped in 2024 when the building was only half complete. The Oregon Bureau of Labor and Industries determined that Minnesota Place LLC had to pay prevailing union wages, which are significantly higher than nonunion wages, while general contractor Lorentz Bruun Co. had bid the project based on nonunion pay.
Court records indicate the prevailing-wage decision was not conveyed to Lorentz Bruun until midway through construction, and the resulting communication breakdown caused a multimillion-dollar shortfall. Minnesota Place LLC asked BOLI to reconsider its decision, and BOLI denied the request. The developer then asked Oregon Housing and Community Services to fund the gap between prevailing and nonunion wages, and the state denied that request as well. The project became the subject of two lawsuits in Multnomah County Circuit Court involving BOLI, Minnesota Place LLC, Lorentz Bruun and its subcontractors, and the building has stood unfinished and vacant while the parties litigated for two years…