A neighborhood group opposed to construction of the $2.1 billion Bull Run water filtration plant isn’t giving up yet.
In Brief:
- Cottrell files new legal appeal over Bull Run water project
- Multnomah County had approved project construction
- Critics say natural resources weren’t fully considered
- Portland must meet 2027 safe water deadline
On Friday, an attorney for the Cottrell Community Planning Organization filed a notice of intent to appeal a Multnomah County hearings officer’s determination that the infrastructure project could proceed.
The Cottrell group earlier appealed a county hearings officer’s determination to the state Land Use Board of Appeals. Then in January, LUBA remanded the matter back to a hearings officer…