Lambert Airport moves closer to new terminal as design work progresses

ST. LOUIS, Mo. (First Alert 4) – St. Louis Lambert International Airport is moving forward with plans to modernize its facilities, with new details showing steady progress toward a potential new terminal.

Airport leadership says the project is approaching a key milestone, with 30% of the design work expected to be completed in early April, a slight delay from earlier timelines discussed at the start of the year. That would mark a significant step in turning the long-discussed “one terminal” concept into a more defined plan.

According to the presentation, the project timeline includes:

  • 30% design completion in early April
  • 60% design completion targeted for early fall
  • Final design and potential groundbreaking in 2027

The proposed overhaul is part of a broader, long-term master plan aimed at modernizing airport infrastructure and operations…