Construction on the Interstate 94 bridges over the St. Croix River between Hudson and Lakeland, Minn., is now complete, according to a Wisconsin Department of Transportation official.
“It’s done,” Christena O’Brien, WisDOT Northwest Region communications manager, told the Star-Observer on Wednesday.
WisDOT said on its website that the project included the following work:
Both bridges:
- Replacing the modular and expansion joints.
- Placing a new polymer overlay on the bridge decks.
- Making concrete surface repairs.
- Cleaning bridge bearings.
- Replacing pavement markings.
Westbound bridge:
- Repairing the east and west abutment back walls.
- Spot-painting the bridge’s pin and hanger system.
Eastbound bridge:
- Repairing the east abutment back wall.
- Replacing the sidewalk railing.
Wisconsin approach:
- Replacing the block retaining wall that crosses under and runs next to I-94, parallel to the pedestrian path.
The rehabilitation project started in April and ran into November, leading to multiple lane closures and traffic jams…