DRAPER — Crews are making progress on “The Point” redevelopment project, but it is hard to see because most of it is underground.
“We’re currently working on the underground utilities, storm drain, sewer, water, and some of the outfall with the ‘River-to-Range’ is going on right here in front of us,” said Project Superintendent Shane Mecham.
Excavation teams throughout this expansive project are laying six miles of pipe. And they have moved enough dirt to halfway fill the University of Utah’s Rice Eccles Stadium.
Leaders have identified the location of one centerpiece of the project, an entertainment venue, which they believe will be a catalyst for the development…