Old Coal Plant Site in Parrish Now Powers 9,000 Homes With Giant Batteries

A seven-acre patch of land in Parrish that once burned coal to light up Alabama homes is now doing something very different: storing electricity in rows of massive batteries. Alabama Power’s Gorgas Battery Facility began serving customers on Oct. 30, six months ahead of its original schedule, and company officials say it can power about 9,000 homes for up to two hours by discharging up to 150 megawatts of stored electricity.

The facility sits on the former site of Plant Gorgas, a coal-fired power plant in Walker County that generated electricity from 1917 until it was retired in 2019, according to al.com. The new system connects to and charges directly from the electric grid and relies on lithium iron phosphate batteries, the same publication reports. As WBMA reported, the project marks Alabama Power’s first utility-scale battery energy storage facility, built at a site where coal-fired generation helped power the state for more than a century.

Built From Dozens of Tesla Megapacks

The facility’s construction relied on 92 Tesla Megapacks, which together weighed a combined 7.7 million pounds, per the station’s report. Getting that equipment connected to the grid was no small task: project teams logged more than 108,000 hours of work. The cable count differs slightly between accounts — the same report describes installing nearly 35 miles of cable, while al.com’s reporting puts the figure at 35 miles tied to those same 108,000-plus hours of labor.

Alabama Power said the project did not increase customer rates, according to the station’s report. Company officials also said the facility was developed to help Alabama Power evaluate how battery storage can work alongside its existing energy sources as demand grows, with the stored power helping the utility meet changing energy needs and support reliability. Experience gained at Gorgas is expected to inform future battery projects, per the same account.

Ahead of a 2027 Target

The Gorgas facility had an estimated completion date of 2027, making its Oct. 30 start six months ahead of schedule. That timeline marks a shift from earlier planning: a 2025 report from ess-news.com indicated construction was expected to begin in 2025 and finish by 2027, and described the planned system as a standalone lithium iron phosphate facility rated at 150 megawatts with 300 megawatt-hours of storage capacity…