Work paused at Pine Lakes dam due to elevation issues

BOILING SPRING LAKES, N.C. (WECT) – The city of Boiling Spring Lakes has announced that work at the Pine Lake Dam site has been paused.

According to the city, it was observed that water levels in Pine Lake were incorrect after rainfall on June 14, and contractors, consulting engineers, and design engineers were contacted.

Reports show that although the contractor built the dam to the elevation on the plans, the elevation is incorrect…

Story continues