Traffic is now using the first of two new bridges on a project to construct 4 miles of new divided four-lane highway along US 93 between the Phoenix area and Las Vegas.
The bridge over Cane Springs Wash represents one of the most visible signs of progress on an $50 million Arizona Department of Transportation project to widen what is now a two-lane segment of US 93 between Wikieup and Interstate 40. The project, which began in early 2025, is now 75% complete.
The 132-foot-long southbound bridge is the twin of another structure that’s expected to open in late 2026, once crews finish constructing the northbound roadway. The overall project, between mileposts 106-110, is expected to be complete in spring 2027…