The Buena Vista Road diverging diamond interchange is almost complete, and the road closure for the Spiderweb project also edges closer to completion, according to a quarterly update from Columbus Consolidated Government officials during the Nov. 10 city council meeting.
More than $1.2 billion in infrastructure projects are active throughout Columbus, deputy city manager Pam Hodge told the Ledger-Enquirer in March, after a spring update.
Funding for these projects has come from various sources, including:
- 2012 and 2022 Transportation Special Purpose Local Option Sales Tax (TSPLOST)
- TSPLOST Discretionary Funds
- Special Purpose Local Option Sales Tax (SPLOST) 2021
- Other Local Option Sales Tax (OLOST) Infrastructure Fund
- Stormwater Fund
- Paving Fund
- Georgia Department of Transportation
- Private Donations and public-private partnerships
- Columbus Building Authority Bonds.
CCG department directors Vance Beck (engineering), Ryan Pruett (inspections and code) and Will Johnson (planning) presented to the council updates about major infrastructure projects.
Transportation
- The Flood Abatement Project 19th Street System, which runs on the west side of Veterans Parkway from Apex Road to the flood basin near 29th Street, is about 75% complete, Beck reported during the presentation. Crews are installing a new culvert and flood basing to reduce flooding issues.
- The final alignment is open on the Buena Vista Road diverging diamond interchange, which is 90% complete, Beck said. This comes after utility conflicts delayed the $52.7 million project. Crews are finalizing the last pieces of the project, including landscaping, and it should be completed by the end of the year, he said.
- The I-185/Cusseta Road Interchange is 88% complete, Beck said, with completion estimated to be next spring. Its budget is almost $72 million and is funded by TSPLOST. Councilor Bruce Huff asked whether GDOT could add a signal light from the southbound side of this project, despite the traffic study finding that it isn’t warranted. A traffic study wouldn’t be able to determine “what’s coming because it’s never been there,” Huff said.
- Work on the SR 1/US 27 widening on Veterans Parkway is about 62% complete, Beck said, and is estimated to be completed next summer. A traffic signal is being installed at the Dekalb Drive intersection, he said, so it will be safer for drivers turning onto Veterans Parkway. The budget for this project is about $72.3 million.
- The Spiderweb Phase II project is about 61% complete, Beck reported, and is expected to be completed in April.
- A new road from South Lumpkin Road to Fort Benning Road, and a trail along Fort Benning Road, are part of the Infantry Road and Follow-Me Trail project. This $2.4 million project expected to be completed next spring.
- The Dragonfly Trails Midtown Connector Phase 1 project will connect a multiuse trail to the existing trail at the intersection of Warren Williams Road and Wynnton Road, following Bradley Drive and Warren Williams Road to Dinglewood Park. The trail continues on to the intersection of 18th Avenue and 13th Street. This project is expected to be completed in April and has a budget of about $1.49 million.
- Crews have successfully staged the Northstar Drive at Kennedy Street Roundabout project to not impact school traffic, Beck said. This project has a budget of about $2.4 million and is expected to be completed in the first quarter of 2027.
The city has also been working on sidewalks and accessibility improvements, Beck said, including completing sidewalk upgrades on Double Churches Road, Front Avenue and under the 13th Street Bridge…