Texas Governor Greg Abbott has directed state regulators to conduct a thorough audit of pending data center projects seeking connections to the state’s electric grid. This initiative comes amid rapidly increasing electricity demand fueled by the growth of artificial intelligence infrastructure, and it effectively places these projects on hold, according to the Electric Reliability Council of Texas (ERCOT).

On Monday, Abbott instructed both the Public Utility Commission of Texas (PUCT) and ERCOT to review all pending data center applications. The agencies are to deny grid access to any facilities that do not meet the state’s established requirements. ERCOT confirmed to Fox News Digital that this directive “effectively pauses all data center projects.”

In a statement, ERCOT said it is working closely with the PUCT to carry out the governor’s orders, including delaying the Batch Zero transmission planning study, a key component in managing grid expansion.

The surge in electricity demand is largely driven by the expanding footprint of AI and cloud computing data centers in Texas. ERCOT revealed that approximately 90% of the 474 gigawatts of large-load interconnection requests currently under consideration are from data centers-surpassing the state’s record peak electricity usage by more than fivefold.

Governor Abbott emphasized that protecting the safety and quality of life for Texans remains the state’s highest priority. As part of the review process, regulators will collect more detailed information from companies, including their plans for self-generating electricity, estimated annual and peak power needs, water usage, and water sourcing strategies.

This latest directive follows Abbott’s recent calls for stricter oversight of the booming data center industry. Last week, he insisted that new AI data centers in Texas should provide their own power, implement water reuse practices, and help reduce electricity costs for residents.

Texas has emerged as a leading hub for data center development, aided by substantial tax incentives. The Texas Tribune has reported that the state offers over $1 billion annually in tax breaks for qualifying projects, fueling rapid expansion.

PUCT Chairman Thomas Gleeson affirmed the commission’s commitment to collaborating with ERCOT to fulfill the governor’s directive. “We appreciate Gov. Abbott’s leadership and will ensure these requirements are fully implemented on behalf of Texans,” Gleeson said.

As the state navigates the challenges posed by surging energy demand, officials continue to balance growth with the need to maintain a reliable and affordable power grid for all Texans.