COHOES, N.Y. (NEWS10) — The City of Cohoes has provided an update on a construction project on Columbia Street. Officials detailed the timeline of the work that began on Monday, May 4, that is to be completed by Friday, May 15.
First on the list is the continuation of sidewalk and curb installation. Pipe work will also begin from Baker Avenue to Simmons Avenue.
Crews will also install storm water catch basins and remove utility poles. Areas that are ready will receive topsoil, be seeded and have mulch spread. Driveways will also be asphalted…