Longboat’s five-year plan top-loaded with pricey projects

Big projects are on the horizon in the next couple of years on the barrier island of Longboat Key, including the installation of an underwater sewage pipeline, which Town Manager Howard Tipton describes as “the most complicated project the town has ever taken on.”

Expected to break ground in the coming months, the installation of a 20-inch-wide plastic pipe from Longboat Key, under Sarasota Bay to the mainland is No. 1 on the town’s list of priorities. It’s expected to cost $42 million, though the town hopes the bill comes in lower.

“We are in the midst of negotiating those costs downward where we can,” Assistant Town Manager Isaac Brownman said…

Story continues

TRENDING NOW

LATEST LOCAL NEWS