Roundabout Project Advances at Scio Church and Zeeb

Work continues on the new roundabout at the intersection of Scio Church and Zeeb roads in Lodi and Scio townships, with crews completing installation of the underground storm sewer this week.

According to the Washtenaw County Road Commission, contractors have also begun grading and compacting the roadway in preparation for new concrete curb installation, which is scheduled to begin in early August.

The intersection remains closed to all traffic. Motorists are advised to follow the posted detour, while truck traffic is being directed to use Pleasant Lake and Wagner roads…