LAX people mover 99% complete but faces new deadline concerns

LAX’s long-delayed people mover is now more than 99% complete, but new financial concerns and a growing dispute between airport officials and the project’s contractor are raising questions about whether the train can meet its latest deadlines.

Fitch Ratings recently placed the credit rating of $1.2 billion in senior bonds tied to the Automated People Mover, dubbed Skylink, on negative watch, according to the Los Angeles Times. The agency also reportedly downgraded the bonds from BB+ to BB, pushing them further into junk territory.

The move comes as the $3.3 billion project approaches two critical deadlines: an Oct. 8 lenders’ deadline and a Dec. 8 project deadline.

Fitch warned that additional delays leave the project with little room before those deadlines are breached. In a worst-case scenario, lenders could demand repayment and the contract between Los Angeles World Airports and LAX Integrated Express Solutions, or LINXS, could ultimately be terminated…

Story continues

TRENDING NOW

LATEST LOCAL NEWS